Hillarys Plaza Taking Shape!

AGEM Property GroupAll News, Projects

Construction Update – January 2019

Hillarys Plaza is starting to take shape with the undercroft car park slab poured and set, ready for the following works to take place in February:

  • Installation of the undercroft pre-cast panels + waterproofing.
  • Back filling of the undercroft panels allowing us to continue with hydraulic works and concrete works on ground floor.
  • Form work installed and concrete poured for the suspended slab above the undercroft

In the background the pre-cast panels will commence casting for the ground floor and in March the ground floor concrete slab poured.

With Hillarys Plaza due for completion November 2019, the centre is over 60% leased and only limited spaces remain available for medical consulting, cafe and office space.